Common triggers

  • Concealed rot, water damage, framing movement, or missing water-management details exposed during removal.
  • Existing dimensions or conditions that differ materially from the documented assumption.
  • Owner-requested product, finish, grid, hardware, or scope changes after approval.
  • Local review or permit requirements that add documented work.
  • Lead-safe containment or related work not included in the original assumptions for applicable pre-1978 painted surfaces.
  1. Stop at the affected scope

    Protect the opening and avoid covering the condition before it is documented.

  2. Record the evidence

    Use photographs, measurements, and a plain-language description tied to the opening identifier.

  3. Present options

    Separate work needed to continue from optional improvements or broader repairs.

  4. Price and schedule the revision

    State additions, credits, payment timing, product changes, and schedule effect.

  5. Approve in writing

    Use the contract's authorized change process before proceeding.